Lee Company was presented with a gnarly problem. This manufacturing facility’s process water was filthy, and they needed it cleaned up pronto. Fortunately, the Lee Company team was ready with the ideal fix: a shiny new process chilling system for their site. Problems? Pfft! Consider it taken care of!

This project required a concerted effort from everyone involved. From the fabrication shop to the electricians to the controls team, all hands were on deck. The synergy was exceptional as the team worked diligently to meet deadlines and deliver high-quality results. Together, they transformed a significant problem into a comprehensive turnkey solution, greatly satisfying the customer. The collaborative effort ensured the project’s success and provided the customer with a reliable and efficient system.

Square Footage:

4,500+ linear feet of Process Water Piping and prefabricated 12’ x 8’ Pump/HX Skid.

Duration: 6 months

Scope of Work:

  • Complete replacement of chilled water system mechanical room in 5 days.
  • Engineering, design, and fabrication of a decoupled chilled water equipment skid including pumps, HX, bag filtration, chemical injection points, controls, and functional testing.
  • Installation of more than 4,500’ of 4” and down main and distribution supply & return piping throughout an active automotive manufacturing facility.
  • Turnkey installation and operation for client once all is in place and tested. Including but not limited to engineering, design, mechanical piping, electrical, controls and tab.